Qinghai Delingha 50MW CSP Station
On December 30, 2018, it was connected to the grid for power generation;
The total investment exceeds RMB 1 billion;
It covers an area of 3.5 square kilometers, with 27135
heliostats, each heliostat covering an area of 20 square meters, and
the heat absorption tower is 200 meters high;
Designed annual power output: 146 million kWh;
The achievement rate of power generation has continuously
exceeded 100%, making it the first CSP and molten salt energy
storage power station with an annual power output exceeding the
annual design power output in China and even in the world!